Service installation requirements

Before service can be installed, the following conditions need to be met:

  • The construction site and building foundation must be back-filled to within 3" of final grade.
  • The service route is to be cleared 10' wide of brush, etc.
  • The gas meter location must be clearly marked.
  • Easements need to be signed and on file with MGU.
  • All service construction charges are to be paid in advance.